In 1927 two Fraser Lake residents, Charles Foote and Alfred Langley found
many fragments of mineralized boulders scattered along a ridge 8.5 kilometres
southwest of a village called Endako. The two men had come to hunt - they
stayed to strike claims. Later they sank an 8 metre shaft in a quartz
molybdenite vein and drove a short adit below the shaft. But 30 years passed
before sufficient exploration revealed the presence of a major ore body and
before the space-age demand for molybdenum made development an economic
possibility.

Endako Mines Ltd. (N.P.L.) was incorporated in June, 1962 and in August of
the same year Placer Development Limited, a predecessor company of Placer
Dome Inc., entered into an option agreement with Endako.

Clearing and construction began in March, 1964 and the project was completed
in May, 1965 after an expenditure of some $22 million. The mine had
progressed from its first drill hole to commencement of mill production in
slightly more then three years.

Mill output increased gradually to a rate of 16,000 tonnes per day in 1967.
Later the same year, an expansion of mining facilities increased capacity
to 24,000 tonnes per day. By 1980 improved production methods
had increased mill output to 28,000 tonnes per day.

In 1971 Endako Mines Ltd. (N.P.L.) amalgamated with Placer Devolpment Limited
and eventually became a division of Placer Dome Canada Limited. As a result of poor worldwide economic conditions and deterioration in global
molybdenum markets, operations at Endako were suspended in 1982, although
Endako maintained a continuous supply of product from inventory. Mining and
concentrating were resumed at reduced capacity in 1986. By early 1989 mining
and milling had returned to full production of 28,000 tonnes per day.
Thompson Creek Mining Ltd. and Nissho Iwai Moly Resources Inc. formed a joint venture
and acquired the operations from Placer Dome in 1997.